Administrative Organization of Tonami Koikiken
GreenLeaf Filter has been continuously evaluated for its stable operation
DB project for expansion of the Water Treatment Plant capacity within the same area of the existing Plant using the same sand filtration method
DB project for which a water treatment company acts as a representative of the Joint Venture, the first domestic project
A water treatment company acts as a representative company of the entire JV and promises reliable construction work.
Consideration of maintenance and management
The flow had to be the same as the existing one considering the maintenance and manageability of the existing water treatment plant to be operated simultaneously.
In particular, with regard to the filtration method, which is the core of water treatment, we proposed and adopted Greenleaf Filter, which was the same type & shape as the existing one. Moreover, additional function of cryptosporidium counter measure was also adopted.
Build water treatment facility by integrating mechanical and electrical equipment
Our scope was full package for not only mechanical equipment but also electrical equipment.
Especially with regard to electrical equipment, it was designed & installed with excellent maintainability and necessary & sufficient functionality by our experienced electrical engineers familiar with water treatment.
Business Overview
Project Name
Design and Build Lump-sum order for renewal of the Matsushima Water Treatment Plant
Employer
Administrative Organization of Tonami Koikiken
Contractor
Joint venture of Swing, Tonami, Fujii, Umemoto, and Chuo Design for Construction Work
Project Period
from April 2014 to March 2018
Facility capacity
25,000m3/day (total capacity 50,000m3/day)
Business Type
DB(Design-Build)
Construction record
Full view before the start of construction
Under creation work in April 2015
Foundation work (deep mixing improvement) in June 2015
Foundation work (deep mixing improvement) in August 2015
Frame work (sedimentation tank and filtration tank bottom slab completed, sidewall construction in progress) in October 2015
Frame work (under construction of sedimentation tank sidewalls) in December 2015
Frame work (casting completion of the sidewall of the sedimentation tank) in January 2016
Frame work (inflow ditch construction in progress) in March 2016
Frame work (casting completion of inflow ditch) in May 2016
Frame work (framework of sedimentation tank completed) in July 2016
Frame work (construction in progress of sedimentation tank roof and completion of framework of filtration tank) in September 2016
Civil engineering and construction work (construction in progress of sedimentation tank roof exterior and framework of rapid filtration tank roof) in November 2016
Finishing work for outer wall of rapid filtration tank roof in February 2017
Mechanical Completion, trial operation started in November 2017