GreenLeaf Filter has been continuously evaluated for its stable operation

DB project for expansion of the Water Treatment Plant capacity within the same area of the existing Plant using the same sand filtration method

DB project for which a water treatment company acts as a representative of the Joint Venture, the first domestic project

A water treatment company acts as a representative company of the entire JV and promises reliable construction work.

Consideration of maintenance and management

The flow had to be the same as the existing one considering the maintenance and manageability of the existing water treatment plant to be operated simultaneously.
In particular, with regard to the filtration method, which is the core of water treatment, we proposed and adopted Greenleaf Filter, which was the same type & shape as the existing one. Moreover, additional function of cryptosporidium counter measure was also adopted.

Build water treatment facility by integrating mechanical and electrical equipment

Our scope was full package for not only mechanical equipment but also electrical equipment.
Especially with regard to electrical equipment, it was designed & installed with excellent maintainability and necessary & sufficient functionality by our experienced electrical engineers familiar with water treatment.

Business Overview

Project Name

Design and Build Lump-sum order for renewal of the Matsushima Water Treatment Plant

Employer

Administrative Organization of Tonami Koikiken

Contractor

Joint venture of Swing, Tonami, Fujii, Umemoto, and Chuo Design for Construction Work

Project Period

from April 2014 to March 2018

Facility capacity

25,000m3/day (total capacity 50,000m3/day)

Business Type

DB(Design-Build)

Construction record

Full view before the start of construction

Under creation work in April 2015

Foundation work (deep mixing improvement) in June 2015

Foundation work (deep mixing improvement) in August 2015

Frame work (sedimentation tank and filtration tank bottom slab completed, sidewall construction in progress) in October 2015

Frame work (under construction of sedimentation tank sidewalls) in December 2015

Frame work (casting completion of the sidewall of the sedimentation tank) in January 2016

Frame work (inflow ditch construction in progress) in March 2016

Frame work (casting completion of inflow ditch) in May 2016

Frame work (framework of sedimentation tank completed) in July 2016

Frame work (construction in progress of sedimentation tank roof and completion of framework of filtration tank) in September 2016

Civil engineering and construction work (construction in progress of sedimentation tank roof exterior and framework of rapid filtration tank roof) in November 2016

Finishing work for outer wall of rapid filtration tank roof in February 2017

Mechanical Completion, trial operation started in November 2017