Loading

Gojo City Clean Oasis

State-of-the-art night soil treatment plant employing phosphorus recovery technology as well as sludge to combustion improver transformation technology

The city of Gojo located in Nara Prefecture is full of natural richness and romantic history with world heritage "Omine Okugakemichi."
In March 2015, we completed a new type of night soil treatment plant that incorporates state-of-the-art material recycling technology that takes environmental conservation into consideration.

The condition for renewal of the aging facilities was pursuit for further economic efficiency

In Gojo City, while it was desirable to renew its aging night soil treatment facilities after 34 years of operation, public sewerage improvement projects were also proceeding, and the volume of night soil and other waste was expected to be reduced. Therefore, the key to the problem solution was to treat sewage more economically.

In response to the demand for "construction of economically efficient sludge treatment facility for night soil and septic tanks," we selected a direct dewatering (pre-dehydration) denitrification treatment system, which features a simple treatment flow, and reduced both construction and maintenance costs.

Hybrid resource recovery technology that produces sludge combustion improver and recovers phosphorus at once

The "Subsidy for Establishment of a Sound Material-Cycle Society" under the jurisdiction of the Ministry of the Environment is utilized by adopting the sludge to combustion improver transformation and the phosphorus recovery method (MAP method, the first adopted project for Swing).
For direct dehydration of night soil, we adopted shaft sliding type screw press dehydrator which is easy to maintain and the most used in the industry for combustion improver.
For separated wastewater treatment, we have introduced a denilite system (our new standard technology) that has the same or greater performance as the membrane separation high-load denitrification process without using pre-treatment facility or membrane separation equipment. It also contributes the reduction of LCC.

Completed in March 2015

We undertook all work (Design-Build), from facility design to material procurement, civil engineering and construction, machinery and electrical equipment installment, while giving consideration to the safety of the local community.

Before the start of construction on July 4, 2013

Basement drilling on November 6, 2013

Reinforcement for basement on December 10, 2013

Reinforcement for basement on December 17, 2013

1st floor slab reinforcement on February 11, 2013

2nd floor slab pasted on April 8, 2014

Slab Reinforcement on the R floor on June 25, 2014

Soundproof net installed on July 1, 2014

Equipment installation and piping work on September 24, 2014

Outer construction work (1) on November 27, 2014

Outer construction work (2) on February 2, 2015

Outer construction work (3) on March 7, 2015

Completed on March 23, 2015